Algonics Start a project

Power and monitoring for railway signalling

We design integrated power supplies for signalling and telecom to RDSO specifications, and a browser-based system that shows every track circuit, signal and level-crossing gate in an automatic section as it changes.

Three tall grey LC-IB-RH power supply cabinets marked Indian Railway Property, with rows of meters and modules
LC-IB-RH power supply panels for level-crossing gates, built to RDSO/SPN/215/2018.
  • RDSO/SPN/165/2023Integrated power supply, Version 4.0
  • RDSO/SPN/215/2018LC gate IPS, Version 2.0, declared technically OK
  • Two zonal railwaysTrain monitoring in service since 2013
  • 901 relay inputs69 km of track on 16 PLCs

Integrated power supply to RDSO/SPN/165/2023

One SMPS-based system that delivers stable, uninterrupted AC and DC to every signalling circuit (point machines, signal lamps, track circuits, axle counters and block instruments) through every mains variation and outage.

Older yards fed each circuit from its own supply and battery, which was costly and left signals blank during outages. An IPS conditions the mains once and derives every AC and DC voltage from one system on one battery bank.

Algonics designs the modules, firmware and DSA. OEM manufacturers license the production-ready design and take it to approval and volume manufacture under their own brand.

What the system consists of

FRBC charger panel
Switch-mode float-cum-boost chargers, 110 V, 20 A per module, in N+1 load sharing with automatic float/boost changeover and programmable battery-path limits.
AC distribution
DSP-controlled inverters, 110 V DC in and 230 V AC out up to 1.5 kVA, and voltage-regulated AC-AC converters with adjustable setpoint and automatic changeover.
DC distribution
A bank of hot-swappable DC-DC converter modules generating every signalling voltage, each with its own metering, fault indication and current sharing.
DSA and remote monitoring
The microcontroller-based supervisory and alarm unit: the operator interface and remote communication for the whole system.
Battery bank and protection
A common 110 V battery with under-voltage isolation, reverse-polarity protection, depth-of-discharge indication and lightning surge protection.
Status panel for the ASM
Battery depth of discharge, mains status and ‘Call S&T’ alerts in the Station Master’s room, without a visit to the equipment room.

A decade of RDSO-verified development

An IPS rack standing on stage at the STE Seminar 2016, with a presenter at the lectern
The complete IPS rack demonstrated live at the STE Seminar 2016.
  1. 2014

    Engagement with Urban Engineering

    Algonics engaged as design consultant for railway power system development, starting a multi-year programme of RDSO-specification power supplies.

  2. 2016

    Live demonstration to S&T engineers

    The full IPS rack presented and demonstrated at the STE Seminar 2016 before Indian Railways signal and telecom engineers.

  3. 2017

    First completion certificate

    Development certified complete after testing against the reference RDSO specification in the presence of RDSO officials, with satisfactory results.

  4. 2018–19

    LC gate IPS to RDSO/SPN/215/2018 Ver 2.0

    Level-crossing IPS with solar PV and MPPT. Certified in March 2019 after repeated tests before RDSO officials at our works: within specified limits and declared technically OK by RDSO, pending only environmental, dust and vibration tests at an approved laboratory.

  5. 2023–now

    Station IPS to RDSO/SPN/165/2023 Ver 4.0

    Station-class prototype racks to the latest specification: FRBC chargers, inverters, AC-AC converter, DC-DC bank and DSA with remote monitoring, engineered for OEM manufacture.

How power moves through the rack

  1. InputsGrid or DG set, 150–275 V AC, with Class B and C surge protection; solar PV on LC gate panels
  2. ChargersFRBC float-cum-boost chargers in N+1; MPPT for solar
  3. Battery bankOne 110 V signalling battery, temperature-compensated charging
  4. ConvertersInverters, AC-AC converters and the DC-DC bank
  5. S&T loadsPoint machines, signal lamps, track circuits, axle counters, block instruments

DSA and remote monitoring unit watches every stage and raises a named alarm for the failed module.

Built for the relay room

  • Wide AC input tolerance with automatic out-of-range cut-off and restore
  • High-frequency switch-mode conversion, high power factor and low THD
  • N+1 parallel redundancy with active load sharing across modules
  • Hot-swappable modules, replaced in under 20 minutes without shutdown
  • Overload, short-circuit, over- and under-voltage, reverse-polarity, and Class B and C surge protection
  • Automatic float-cum-boost battery management with temperature compensation
  • Digital voltage and current metering on every module in the rack
  • Solar PV with MPPT for LC gate variants at remote crossings

What the DSA reports

A backlit LCD cycles live voltages and currents. Setpoints are set from push-buttons, alarms are acknowledged on the panel, and a QR code links to the unit’s documentation. Every fault below is annunciated and logged individually.

  • Mains fail; mains volt low or high
  • Inverter 1 and 2 fail
  • SMR / FRBC fail
  • DC-DC converter fail
  • AVR / AC-AC converter fail
  • Transformer-rectifier fail
  • Surge protector fail
  • Fan fail; fuse fail
  • Communication status
  • Battery disconnected or failed
  • Battery discharged and isolated
  • Mains on with battery on load
  • Temperature compensation fail
  • AC bus fail or overload
  • Output voltage high; overload
  • Solar voltage and current (LC gate)
  • Depth of discharge to the ASM

Technical particulars

Representative module specifications, from the RDSO specification family our prototypes were designed and tested to. Configuration-specific datasheets on request.

System

Input voltage
230 V AC nominal (150–275 V)
Frequency
50 Hz (48–52 Hz)
Supply source
Grid, DG set, solar PV (LC gate)
Redundancy
N+1 parallel load sharing
Module replacement
Hot-swap, under 20 minutes
Ambient rating
System 55 °C; modules 70 °C

FRBC module

Rating
110 V, 20 A per module
Charging
Automatic float and boost; programmable voltages, auto-float delay
Regulation
±1% (25–100% load)
Efficiency
>90% at rated load
Ripple, no battery
<300 mV p-p
Battery path limit
Programmable, 5–15% of Ah

Inverter module

Input
110 V DC (98–138 V)
Output
230 V AC, 50 Hz ±1%
Capacity
500 VA, 1 kVA, 1.5 kVA
Regulation
<±2% (25–100% load)
Waveform distortion
<8%
Protections
Overload, short circuit (auto-reset), DC over- and under-voltage, fan fail

DC-DC converter module

Input
98–138 V DC
Output
Per the railway block diagram
Regulation
±1% of set value (10–100% load)
Ripple
<50 mV p-p
Current sharing
Within 10% between modules
Protections
Overload at 105%, tracking over-voltage

DSA and monitoring

Display
Backlit LCD, live voltages and currents
Setpoints
Push-button entry, saved on hold
Alarms
Individually annunciated, logged and acknowledged
Remote
Remote monitoring unit; status panel for the ASM
Documentation
QR link on the faceplate

AC-AC converter

Output
110 V AC, regulated
Capacity
500 VA, 1 kVA, 1.5 kVA
Setpoint
Adjustable, 110–130 V
Changeover
Automatic
Protections
Overload, short circuit
Interface
Remote communication

Configurable from wayside station to level crossing

Installation classTypical application
Up to 4-line wayside stationSmall PI stations, RE and non-RE areas
4–6 line wayside stationMid-size PI stations
6–10 line medium stationPI and EI stations, signalling load up to 15 kVA
Interlocked LC gateLevel crossings with solar PV and MPPT to RDSO/SPN/215/2018
IBS locationIntermediate block signalling installations

What an OEM receives

Design package
Schematics, PCB Gerbers, BOM and mechanical constraints: a complete manufacturing-ready set.
Firmware and source
DSP and microcontroller firmware for every module and the DSA, on Microchip toolchains, with documented source.
Prototypes and FAT support
Working racks demonstrated at our works, with support through factory acceptance testing and RDSO verification.

Power for level-crossing gates to RDSO/SPN/215/2018

LC-IB-RH power supply panels for Urban Engineering, to Version 2.0 of the specification. Solar PV feeds an MPPT charger alongside the mains, a bidirectional inverter powers the gate equipment, and the DSA’s LCD names the fault instead of showing a single alarm lamp.

Tested repeatedly before RDSO officials at our works, the panel was found within specified limits and declared technically OK by RDSO in March 2019, pending only environmental, dust and vibration tests at an approved laboratory.

  • Fault annunciation for battery, mains input, AC bus and overload, inverter, MPPT charger, DC-DC, transformer-rectifier, solar input, surge protector and fan
  • Solar voltage and current on the LCD, with page-through menus on the panel front
  • Completion certificates in 2017 and 2019

IPeTMS

IP-enabled train monitoring

A web application that reads the relay contacts in every hut of an automatic signalling section and draws the whole section, live, in any browser on Railnet: track circuits, signal states, point machine positions and LC gates. Built by the Urban–Algonics joint venture, tested against RDSO specifications and in revenue service on Eastern and South Eastern Railway since 2013.

How IPeTMS reads an automatic signalling section Two running lines between Station A and Station B are split into track circuits with automatic signals at each block. An UP train occupies the third block, so the signal behind it shows red, then yellow, then double yellow; a DN train occupies the fourth block and an LC gate there is closed. Each relay hut has a PLC reading relay contacts. The PLCs are joined by Ethernet over a spare copper pair of the signalling quad cable using G.SDHSL modems, to a server and database at Station A, which connects over E1 to Railnet, where station masters, maintenance staff and divisional headquarters view it in a browser. Station A Station B UP DN UP train DN train LC gate closed Relay hut 1 PLC reads relays Relay hut 2 PLC reads relays Relay hut 3 PLC reads relays Relay hut 4 PLC reads relays Relay room PLC reads relays Relay room PLC reads relays Ethernet on a spare copper pair of the signalling quad cable, through G.SDHSL modems Server and database at Station A E1 link Railnet railway intranet Station master Maintenance Divisional HQ
How the system sees a section. Each relay hut’s PLC reads spare, potential-free relay contacts for track circuits, signal aspects, points and gates, and publishes them over the section’s own copper. The server logs every change and serves the picture to browsers.

Two sections, documented

South Eastern Railway: Santragachi–Tikiapara

Pilot in the Kharagpur division under Indian Railways Vision 2020 for unified IP communication, in continuous operation from January 2013. Documented by SER’s Chief Signal Engineer in IRISET’s Gyandeep.

Auto section
3.5 km
Track covered
14 km
Stations
Santragachi (outer), Ramrajatala, Das Nagar, Tikiapara (outer)
Relay huts with PLCs
8
Relay inputs wired
282
Server
1, at Santragachi, on Railnet

Eastern Railway: Dankuni–Kamarkundu

Commissioned 21 May 2013 and running from 31 May 2013 under the section’s full traffic of 215 trains a day: 70 local, 105 mail and 40 goods. The performance report records it as reliable and stable, with trouble-free working.

Auto section
15 km
Track covered
55.12 km
Stations
Dankuni (outer), Gobra, Janai Road, Begampur Halt, Baruipara, Mirzapur-Bankipur, Balarambati, Kamarkundu (outer)
PLC locations
8
Relay inputs wired
619
Server
Baruipara relay room, linked to Railnet over E1

What it changed on the ground

The whole section on one screen

Station masters see every track circuit, signal aspect and LC gate between stations. They can see exactly when a train has cleared a gate, which the published report credits with better punctuality.

Faults found from the relay room

The PLC’s ladder logic shows which relay in a circuit failed to pick up, so maintainers can tell a field-gear failure from an internal relay failure.

Every change on record

Each relay transition is stored with a timestamp. Any period can be replayed to diagnose a fault.

No client software

Any computer on Railnet with a standard browser can open it, and any railway engineer can reach it from any relay hut on the LAN. There is nothing to install and no per-seat licence.

Less copper to the station

Repeating auto-section indications to a station normally needs a conductor pair per indication. Here they travel as data on a single spare pair.

Section-wide, not one logger at a time

Conventional data loggers show one RTU or DTL at a time. This system shows every hut in the section together.

Three independent layers

Field. Allen-Bradley MicroLogix 1400 PLCs in each hut, IP-enabled and expandable with digital and analogue I/O cards, wired to spare relay contacts through a tag block.

Network. PLCs as static-IP nodes on a device LAN, extended between huts over existing infrastructure: G.SDHSL modems on a quad-cable copper pair, LAN extenders, Ethernet-to-E1 bridges, or the fibre backbone where the section has one.

Software. An industrial-PC gateway that records all PLC data and keeps a local backup through network outages, and servers on Railnet hosting the database and web application. Any computer at a station, divisional HQ or headquarters becomes an operator terminal, with user access rights. Communication is OPC-compliant, so other vendors’ PLCs and RTUs can join, and concentrators and servers can run dual-redundant or hot-backup.

Each layer can be upgraded without touching the other two. The design also allows non-vital remote control, which SER listed among its goals: changing over the power supply at an auto hut, or operating electric lifting barriers.

Link between hutsReachEthernet bandwidth
Copper quad-cable pair, G.SDHSLUp to 3 km256 kbps minimum
Single-mode optical fibreUp to 20 kmUp to 1 Mbps
2.4 / 5.8 GHz industrial radioUp to 15 kmUp to 1 Mbps

Distances are between adjacent PLC nodes.

In print

Pilot implementation of IP enabled train monitoring and logging system in automatic signalling section

Shri Ajay Kumar, Chief Signal Engineer, South Eastern Railway. Gyandeep technical magazine, anniversary issue 2013. Indian Railways Institute of Signal Engineering and Telecommunications (IRISET), Secunderabad, pages 85–87.

The article sets out why SER chose a browser-based system in line with Indian Railways Vision 2020, how the Santragachi–Tikiapara pilot was built, and what it did for operations and maintenance. It concludes that the system’s “trouble free working” on SER makes the case for wider adoption.

The same platform, beyond rail

Underneath IPeTMS is our general web-based control and data acquisition platform: IP-enabled PLCs and RTUs on a device LAN, gateway data concentrators that keep a local copy when the network drops, and a central server for browser clients. Legacy Modbus and Profibus devices map onto it through converters.

It suits pipeline monitoring, substation SCADA, distributed plant automation and asset management. Our other monitoring work, cooling-tower telemetry for Paharpur and solar irrigation with IIT Mandi, follows the same pattern of field sensors, a resilient link and a browser view.

Planning a section or an IPS order?

Include the ratings, the standard it has to meet and your expected volumes. An engineer reads every enquiry.

info@algonics.com

Kolkata

Module 318, 2nd Floor, S.D.F. Building
Block GP, Sector V, Salt Lake
Kolkata 700091, India

Office +91 33 4004 2846
Mobile +91 94778 08318

New Jersey

14 Eastwood Blvd
Manalapan, NJ 07726
United States

+1 646 493 5057